June 3rd Site Visit…

The cabinets have arrived and are temporarily staged on the north side of the building.

Server Cabinets Server Cabinets

The chiller pipes are now insulated and the loop is complete.

Chiller Pipes Chiller Pipes

The ceiling grid is about 75% installed.  Overhead lighting as well…

Lights and Ceiling Lights and Ceiling

Tomorrow the chillers and UPS’s arrive, and the follwoing day the generators will be delivered.