June 2018
M T W T F S S
« Jun    
 123
45678910
11121314151617
18192021222324
252627282930  

June 5th Site Visit…

We are picking up speed this week as the large equipment arrives…

Generators

Generators Generators

Chillers

Chillers Chillers

UPS and battery cabinets

UPS UPS

Maintenance bypass switchgear and PDU’s

Maintenance Bypass Switchgear PDU

One of the NOC offices and some RPP’s

NOC Offices RPP

Late next week they will begin installing the floor tiles in the data center.  When that is complete I believe we will see some dramatic changes in a very short period of time.